Installation of aluminum doors and windows at residential units ongoing up to 16th floor. |
October 16 to November 15, 2010
Installation of aluminum doors and windows at residential units ongoing up to 16th floor.
*NOTE: There is no designated 4th floor.September16 to October 15, 2010
Structural concrete works to date are substantially completed. Installation of windows advances to 5th to 9th floors. Exterior primer painting now covers 18 floors (river channel side).
August 16 to September 15, 2010
Tower B wall plastering and roofdeck waterproofing ongoing
July 16 to August 15, 2010
Masonry works are at 18th floor of Tower B.
June 16 to July 15, 2010
Pending minor concreting works is the tower crane block-out at ground and 3rd floors respectively.
May 16 to June 15, 2010
Topping off ceremony of Tower B signals start of finishing works
April 16 to May 15, 2010
Concrete hollow block walls and plastering works are at 8th floor.
March to April 2010
Tower B columns and floor slab reached 16th level. Construction of exterior precast wall still ongoing.
February 16 to March 15, 2010
Concreting status to date is already at 10th Floor of Tower B. Exterior precast wall installation is still currently ongoing.
January 16 to February 15, 2010
Work accomplishment is generally on-schedule with an overall actual physical accomplishment of 33.20 % as against a target of 32.09 % as of 14 January 2010. Fair weather continues to grace the month which maximizes a good working pace for construction operations, especially for work shifts and material deliveries. December 16 to January 15, 2010
Concreting status to date is already at 3rd floor of Tower B. Fair weather continues to grace the month which maximized a good working pace for construction operations, especially for work shifting and material deliveries.
|