On-going completion of waterproofing of landscape area at 3rd floor taken from 16th floor Tower A.

October to November 2010

TowerA
Tower A - top


On-going completion of  waterproofing of landscape area at 3rd floor taken from 16th floor Tower A.

*NOTE:  There are no 4th, 13th and 14th floor designations

September to October 2010

Tower A Solemare Parksuites



Structural concrete works to date are substantially completed. Installation of windows advances to 5th to 18th floors. Exterior primer painting now covers all sides of 17 floors.

August to September 2010

alt
alt


A Mockup unit almost complete; Amenity area construction ongoing

July to August 2010

alt



Tower A fifth floor mockup unit substantially completed.

June to July 2010

alt
alt
Pending minor concreting works is the tower crane block-out at ground and 3rd floors respectively

May to June 2010

alt
alt
Topping off ceremony of Tower A signals start of finishing works

April to May 2010

alt
alt
Concrete hollow block walls and plastering works are at 16th floor.

March to April 2010

alt
alt
Tower A columns and floor slab already reached the roofdeck. Construction of exterior precast wall still ongoing.

February 16 to March 15, 2010

TowerA TOWERA
Concreting status to date is already at the 18th Floor of Tower A. Major concrete pouring is now focused at tower levels. Exterior precast wall installation is still currently ongoing.

January 16 to February 15, 2010


Work accomplishment is generally on-schedule with an overall actual physical accomplishment of 33.20 % as against a target of 32.09 % as of 14 January 2010.
Fair weather continues to grace the month which maximizes a good working pace for construction operations, especially for work shifts and material deliveries.

December 16 to January 15, 2010


Concreting status to date is already at 10th Floor of Tower A. Fair weather continues to grace the month which maximized a good working pace for construction operations, especially for work shifting and material deliveries.


November 16 to December 15, 2009

CU
alt
alt


October 16 to November 15, 2009

alt
alt
alt
Concreting works already reached the 7th floor of Tower A, while bulk excavation works are in an advanced status at 97 percent. Civil
works for the Sewage Treatment Plant has already been completed.

October 16 to November 15, 2009

alt
alt

Concreting works already reached the 5th floor of Tower A.

August 16 to September 15

alt
alt
Concreting works already reached the 3rd floor of Tower A.

July 16 to August 15

alt
alt


June 16 to July 15

alt
alt